Agendas

Event Sign Up

Links

About Us

Parks

News

FAQ

Permits

Comp Plan

Jobs

Upcoming Meetings

Runner's World

Rent Snyder House

RSS Feed

 

 

 

Butler Warren Road Project to Reduce Congestion
Public Meeting Planned for Spring 2008

The widening of Butler Warren Road will be well worth the wait when completed in about four years. The project is designed to reduce congestion and improve safety along Butler-Warren Road between Tylersville and Bethany roads.   The Southwest Warren County Transportation Study, completed in September of 2005 by the Ohio Kentucky Indiana Regional Council of Governments (OKI), designated the project a high priority. In the summer of 2006 the Warren County Engineer’s Office, in cooperation with the Butler County Engineer’s Office, applied to OKI for Federal Surface Transportation Program (STP) funds, and was awarded funding for the project in the amount of 60 percent of the cost of construction, right-of-way acquisition and utility relocation.  The remaining 40 percent of the cost will be shared equally between the Warren County Engineer’s Office and the Butler County Engineer’s Office.

 Consulting engineer TranSystems began work in May 2007, and is in the early stages of preliminary engineering.  Currently they are in the process of completing the necessary environmental studies and the preliminary roadway alignment alternatives required of federally funded projects. 

 The plan, provided there is no change due to the environmental and preliminary engineering studies, is to add an additional through travel lane in each direction and a center turn lane at designated access points. The cost of the design is being shared equally between the Warren County Engineer’s Office and the Butler County Engineer’s Office.  The total cost of Part One of the design is $400,592.  The cost for Part Two of the design will be determined after Part One has been completed.

The project is estimated to cost $11.3 million for construction, right-of-way acquisition and utility relocation. Funding breakdown is: $6.78 million – Federal funds; $2.26 million – Butler County Engineer’s Office; $2.26 million – Warren County Engineer’s Office.

The following is a tentative schedule:

-          A public involvement meeting is anticipated in the spring of 2008.

 -          Design plans should be completed in early 2009.

-           Right-of-way acquisition should be completed by the middle of 2010.

-          The project should be awarded in late 2010.

-          Construction should begin in early 2011.

For more information about the project contact the Warren County Engineer’s Office at 513.925.3301.